Hyderabad Metro works to be completed soon

     Written by : SMTV24x7 | Fri, Sep 08, 2017, 01:22 PM

Hyderabad Metro works to be completed soon

Hyderabad Sept 8: Hyderabad people's dream project would soon be fulfilled. The Hyderabad Metro Rail Authorities have said that they are confident that all 30 Km Metro construction of Nagole to Miyapur would be completed by October 15.

Recently the CM KCR has invited PM Narendra Modi to inaugurate the metro train during the GES Summit which will be held during November 28-30 in Hyderabad.

HMRL authorities have said that

* There are 25 stations, including the interchange station at Mythrivanam in Ameerpet, all along the 30-km stretch.

* We have completed the construction of the stations and at present electrical and other works are under way.

* Test runs will be conducted from November.

* All the track works on the 30km stretch have been completed.

* successfully completed the civil works at the three bottlenecks at Oliphant Bridge, Begumpet, and Ameerpet interchange stations.

HMRL MD NVS Reddy has said that "we will get safety clearance after trial runs are completed so that commercial operation can be started".